Technical Project Management–for “Streetligt Network System”

  • 1.Introduction

I was a technical project manager for updating a streetlight network system. This system is to improve city’s streetlight system in controlling and managing, and innovate a convenient streetlight network system.

  • 2. Project Objective

To design and innovate an integrated streetlight network system and platform, a recovery plan, and streetlight renovation in 14 months at a cost not to exceed $ 20 million.

  • 3. Milestones

  • Needs assessment report and analyses finished by June 5th, 2015
  • Operation interface design completed by August 5th, 2015
  • Operating system functional code completed by September 25th, 2015
  • Lighting operating system finished by November 30th, 2015
  • Monitoring system constructed by January 25th ,2016
  • LED streetlights installed by May 25th ,2016
  • Monitoring and operating system’s tests and modification completed by July 26th, 2016
  • Recovery plan formulated and trial operation completed by June 26th, 2016
  • Final test and whole streetlights network system and platform finished by September 7th ,2016
  • 4. WBS from MS Project

All WBS screenshot from MS Project.

WBS of Streetlight Network SystemWBS of Streetlight Network System 1 WBS of Streetlight Network System 2WBS of Streetlight Network System 3 WBS of Streetlight Network System 4 WBS of Streetlight Network System 5 WBS of Streetlight Network System 6 WBS of Streetlight Network System 7

WBS of Streetlight Network System 8

  • 5. Status Report

Status Report

  • 5.1.CV,CPI & SV, SPI of Status Report

CV SV